Value Delivered
The Hilton Meadowlands had an abandoned 300-ton coil cooling tower on their roof that had been out of commission since before the current facilities staff were hired. The property was cooled by a single newer unit with limited access for maintenance and repairs.
Our ESCO partner invited ECM to audit the site, and we identified the severely corroded system as a potential source of redundant cooling. By renovating the unit, we added 15 years of expected useful life.
Client Objectives
The client wanted to add cooling redundancy without a huge capital expenditure.
Solutions
ECM provided the following services:
- Removed a basin, heaters, fill, and float, as they were unsalvageable
- Rust removal
- Repairs and patching
- Added our proprietary HVAC Armor coating for the entire tower
At the completion of these services, the tower was ready for recommissioning.
Client Background
Hilton Meadowlands is operated by Hilton Hotels & Resorts, a leading multinational hospitality brand with over 500 properties worldwide.